Wake County, North Carolina, USA

I-40/I-440, Raleigh, NC

600,000 square yards of concrete pavement was broken for removal with 8600 and MHB Badger Breakers® over 3.5 years in 46 phases. Most of the concrete had a NovaChip asphalt layer on top requiring special attention to achieve consistent breaking. This project is one example of Antigo’s ability to coordinate complex scheduling to meet its customers’ needs.

View Break for Removal Media

Project Details

Location

I-40/I-440, Raleigh, Wake County, North Carolina, USA

Existing Pavement

11" thick JPCP with 1" thick asphalt overlay

When

46 phases from April, 2014 to November, 2017