Broke for removal 100,000 square yards of concrete pavement in 4 1/2 days. Broke the passing lane to 18″ minus. Broke the driving lane to 24″ minus to provide better surface for the haul trucks. A MHB Badger Breaker® was used to break the full width of a lane in a single pass.
I-90 WB (Illinois Tollway), east of Rockford, McHenry & Kane Counties, Illinois, USA
10" thick JRCP
June, 2014