Greene County, Missouri, USA

USH 65, Springfield, MO

105,000 square yards of 10″ thick jointed reinforced concrete pavement was broken for removal with MHB Badger Breakers®. This was a fast track project requiring 6 phases of breaking starting on consecutive Sunday evenings. Antigo operated 2 MHBs to complete each phase of breaking in one night shift each time. The contractor then completed the reconstruction of each phase in one week.

View Break for Removal Media

Project Details

Location

USH 65, Springfield, Greene County, Missouri, USA

Existing Pavement

10" thick JRCP

When

Worked Sunday evening into Monday 6 times during July and August, 2017